26 March 2012
MEDIA RELEASE

Canary Wharf Crossrail station works completed ahead of schedule

Crossrail’s first station platform level completes five months early

Major works complete to enable Canary Wharf station to receive the tunnel boring machines for the eastern running tunnels in 2013

Canary Wharf Group plc has completed construction of Canary Wharf Crossrail station’s platform level five months ahead of schedule, making it ready to receive the two giant eastern tunnel boring machines in 2013.



Construction of the Crossrail project began at North Dock in Canary Wharf less than three years ago. Since then the construction team has driven over 1,000 piles and pumped nearly 100 million litres of dock water – the equivalent to 40 Olympic swimming pools. Approximately 300,000 tonnes of material has been excavated from beneath the dock bed and almost 375,000 tonnes of concrete poured.

Canary Wharf Contractors Limited, the construction arm of Canary Wharf Group, has created a station box that is more than 250m long and 30m wide, approximately the same size as One Canada Square laid on its side, Britain’s tallest operational building. Twenty-eight metres below the surface of the dock, twin 7.6m diameter rings are now in place at both ends of the station ready to receive the eastern tunnel boring machines.

Cliff Bryant, Executive Director of Canary Wharf Contractors Limited, said: “We are very proud to have played our part in a project which will benefit London for many generations to come. Credit must be given to our workforce and supply chain, many of them local East Londoners, who have responded to a very challenging brief and delivered it to Crossrail ahead of time and within budget.”

Bill Tucker, Crossrail Area Director Central said: “Construction of Crossrail’s first excavated platform level is now complete and has been delivered five months early by Canary Wharf Group. Preparations will now begin for the arrival of the tunnel boring machines next year. When the tunnelling machines breakthrough into the station box from the east they will undergo maintenance before being moved to the other end of the station box where they will then set off on their journey en route to Farringdon via Whitechapel and Liverpool Street stations.”

Construction of the Canary Wharf Crossrail station box generated approximately 200,000 cubic metres of excavated material. About a quarter of this was reused on site and the rest was reused at regeneration areas including Pitsea and Hoo Island to create habitats for flora and fauna. The majority of the excavated material was removed by barges rather than lorries, saving more than 29,000 lorry trips and reducing carbon dioxide emissions by 780 tonnes.

Crossrail’s eastern tunnelling contractor Dragados Sisk JV will shortly commence enabling works to receive the two tunnel boring machines that will be launched from Limmo Peninsula later this year.

After the TBMs pass through, Canary Wharf Group will fit out the station with work due to complete in 2015. Work will continue to construct the levels sitting directly above the station box.

Canary Wharf Crossrail station will be one of the largest stations on the Crossrail route. Crossrail will dramatically increase the capacity and resilience of transport services to and from Canary Wharf and the surrounding area, helping underpin further development and investment in this key business and shopping district.

Journey times will be cut to many destinations across London. It will take just 6 minutes to travel to Liverpool Street, 8 minutes to Farringdon and 39 minutes to Heathrow. The Crossrail service at Canary Wharf will be 12 trains per hour in each direction during the peak. Crossrail services will commence in 2018.

Canary Wharf Group has planning permission for four levels or 100,000 square feet of retail, topped by a spectacular roof top garden, community facility and restaurant semi-covered by a spectacular timber lattice roof.

Ends

Images of the completed station box are available for download from the Crossrail press image gallery.

For further information please contact: Crossrail Press Office on 020 3229 9552 or email: pressoffice@crossrail.co.uk

Hamish McDougall, Canary Wharf Group Press Office, Tel. 020 7418 2326, Mob. 07779 888 075, Email hamish.mcdougall@canarywharf.com

About Canary Wharf Crossrail station:

In December 2008 Canary Wharf Group plc signed an agreement with TfL, DfT and Crossrail to design and construct the station box for a fixed price of £500m, of which £150m is contributed by Canary Wharf Group.

Crossrail construction commenced on 15 May 2009 when the first tubular 18.5m long pile was lowered into the waters of North Dock at Canary Wharf. The project used a special silent ‘Giken’ piling system which minimises disruption to local businesses and residents. This was the first time this Japanese technology had been extensively used in the UK.

On 26 March 2012, Canary Wharf Group will hand over to Crossrail Limited the station box platform level.

In addition to Canary Wharf Contractors Limited, Arup Engineering acted as the geotechnical, structural and building services consultant; Tony Meadows Associates prepared the station design concept and acted as operations architect; Foster + Partners acted as the project design architect; Gillespies acted as landscape architect for the oversite development’s roof-top park; and Adamson Associates acted as the project executive architect for the oversite development’s retail mall.

About Crossrail:

The total funding envelope available to deliver Crossrail is £14.8bn. The Crossrail route will pass through 37 stations and run 118 km (73 miles) from Maidenhead and Heathrow in the west, through new twin-bore 21 km (13 miles) tunnels to Shenfield and Abbey Wood in the east.

When Crossrail opens it will increase London’s rail-based transport network capacity by 10%, supporting regeneration and cutting journey times across the city. Crossrail services are due to commence through central London in 2018.

Crossrail is being delivered by Crossrail Limited (CRL). CRL is a wholly owned subsidiary of Transport for London. Crossrail is jointly sponsored by the Department for Transport and Transport for London.

About Canary Wharf Group plc:

Canary Wharf Group is an integrated property development, investment and management group of companies.

Canary Wharf has a working population of nearly 100,000 people in a diverse range of sectors for some of the world’s leading companies. It has paved the way for the regeneration of London’s Docklands and one in five Canary Wharf workers now lives in a local East London borough. It has helped London and the City consolidate its position at the centre of the business world.

Following the recent announcement to build a new headquarters for European Medicines Agency at 25 Churchill Place, the Group has plans in place to continue to develop Canary Wharf in the coming years.

Canary Wharf Group also has joint ventures outside Canary Wharf at 20 Fenchurch Street (with Land Securities) and the Shell Centre (with Qatari Diar).

www.canarywharf.com Twitter: @yourcanarywharf